Rail Maintenance Pit
Rail Innovation Centre - Long Marston
Chrysalis Rail LLP had a requirement to instal a 30m rail maintenance pit to enhance their facility at Long Marston.
The scope of work;
Break out concrete and remove the existing rail track
Excavate and dispose arisings off site
Design and build the reinforced concrete rail pit
Install the rails to a +/- 2mm tolerance
Construct jacking slabs to either side of the rail pit