Rail Maintenance Pit

Rail Innovation Centre - Long Marston

Chrysalis Rail LLP had a requirement to instal a 30m rail maintenance pit to enhance their facility at Long Marston.

The scope of work;

  • Break out concrete and remove the existing rail track

  • Excavate and dispose arisings off site

  • Design and build the reinforced concrete rail pit

  • Install the rails to a +/- 2mm tolerance

  • Construct jacking slabs to either side of the rail pit